United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project MPC01800, Burleigh County

Onshore wind project MPC01800, Burleigh County is a 140 MW onshore wind request withdrawn in the MISO interconnection queue, in Burleigh County, North Dakota, connecting to Minnkota Power Cooperative.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
MPC01800
Grid region
MISO (Midcontinent)
Utility / transmission owner
Minnkota Power Cooperative
Connection point (POI)
Center-Jamestown 345 kV Line
Location
Burleigh County, North Dakota
Technology
Wind: 140 MW
Total requested
140 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
22 December 2008
Proposed online date
December 2011

Location

Marker shows the centre of Burleigh County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Burleigh County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem