United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project J1888, Oliver County

Onshore wind project J1888, Oliver County is a 175 MW onshore wind request withdrawn in the MISO interconnection queue, in Oliver County, North Dakota, connecting to MINNESOTA POWER INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1888
Grid region
MISO (Midcontinent)
Utility / transmission owner
MINNESOTA POWER INC.
Connection point (POI)
Square Butte 230 kV Substation East
Location
Oliver County, North Dakota
Technology
Wind: 175 MW
Total requested
175 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
25 January 2022
Proposed online date
April 2024
Withdrawn
October 2025

Location

Marker shows the centre of Oliver County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Oliver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem