United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project H082, Oliver County

Onshore wind project H082, Oliver County is a 500 MW onshore wind request withdrawn in the MISO interconnection queue, in Oliver County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedMay 2011 (project stopped here)
  3. ConsentedMay 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H082
Grid region
MISO (Midcontinent)
Connection point (POI)
OTP Center 345 kV Substation
Location
Oliver County, North Dakota
Technology
Wind: 500 MW
Total requested
500 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
30 June 2008
Agreement signed
4 May 2011
Proposed online date
November 2010
Withdrawn
May 2011

Location

Marker shows the centre of Oliver County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Oliver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem