πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project J511, Oliver County

Onshore wind project J511, Oliver County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Oliver County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2015 (completed)
  2. Withdrawn / abandonedOct 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J511
Grid region
MISO (Midcontinent)
Connection point (POI)
GRE Stanton Substation 230 kV bus, Stanton ND
Location
Oliver County, North Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
16 November 2015
Proposed online date
October 2017
Withdrawn
October 2018

Location

Marker shows the centre of Oliver County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Oliver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem