ONSHORE WIND · MISO

Onshore wind project MPC02100, Oliver County

Onshore wind project MPC02100, Oliver County is a 100 MW onshore wind request built and operating in the MISO interconnection queue, in Oliver County, North Dakota, connecting to Minnkota Power Cooperative.

Queue statusOperating
  1. PlanningQueued Dec 2008 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
MPC02100
Grid region
MISO (Midcontinent)
Utility / transmission owner
Minnkota Power Cooperative
Connection point (POI)
Center - Mandan 230 kV Line
Location
Oliver County, North Dakota
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
12 December 2008
Proposed online date
December 2016
Came online
December 2016

Location

Marker shows the centre of Oliver County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Oliver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem