United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

BATTERY STORAGE Β· SPP

Battery storage project GEN-2022-245, Kidder County

Battery storage project GEN-2022-245, Kidder County is a 200 MW battery storage request withdrawn in the SPP interconnection queue, in Kidder County, North Dakota, connecting to BEPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-245
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
Line tap of existing Leland Olds (Secondary) - Groton 345 kV line
Location
Kidder County, North Dakota
Technology
Battery: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
10 March 2022
Proposed online date
September 2028
Withdrawn
November 2023

Location

Marker shows the centre of Kidder County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Kidder County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem