United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project J090, Mercer County

Onshore wind project J090, Mercer County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Mercer County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2009 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. ConsentedAug 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J090
Grid region
MISO (Midcontinent)
Connection point (POI)
GRE Stanton 230 kV Substation
Location
Mercer County, North Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
8 October 2009
Agreement signed
23 August 2012
Proposed online date
August 2012
Withdrawn
August 2012

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem