United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project G221, Dickey County

Onshore wind project G221, Dickey County is a 180 MW onshore wind request withdrawn in the MISO interconnection queue, in Dickey County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2002 (completed)
  2. Withdrawn / abandonedNov 2002 (project stopped here)
  3. ConsentedNov 2002 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G221
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Dickey County, North Dakota
Technology
Wind: 180 MW
Total requested
180 MW
Queue status
Withdrawn
Entered queue
16 April 2002
Agreement signed
13 November 2002
Proposed online date
June 2005
Withdrawn
November 2002

Location

Marker shows the centre of Dickey County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Dickey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem