United States › Grid › Interconnection queues › North Dakota
ONSHORE WIND · MISOOnshore wind project J3280, Dickey County
Onshore wind project J3280, Dickey County is a 300 MW onshore wind request in interconnection study in the MISO interconnection queue, in Dickey County, North Dakota, connecting to MONTANA-DAKOTA UTILITIES CO..
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3280
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MONTANA-DAKOTA UTILITIES CO.
- Connection point (POI)
- Ellendale
- Location
- Dickey County, North Dakota
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 17 April 2024
- Proposed online date
- September 2028
Location
Marker shows the centre of Dickey County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Dickey County
- Onshore wind project G132, Dickey CountyOnshore wind · 180 MW · built
- Onshore wind project J249, Dickey CountyOnshore wind · 180 MW · built
- Onshore wind project G359R, Dickey CountyOnshore wind · 150 MW · built
- Onshore wind project J316, Dickey CountyOnshore wind · 150 MW · built
- Onshore wind project G853, Dickey CountyOnshore wind · 600 MW · withdrawn
- Gas project J509, Dickey CountyGas · 327 MW · withdrawn
- Onshore wind project GI-0112, Dickey CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project G690, Dickey CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J3667, Dickey CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G713, Dickey CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G221, Dickey CountyOnshore wind · 180 MW · withdrawn
- Onshore wind project G359, Dickey CountyOnshore wind · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem