United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project G690, Dickey County

Onshore wind project G690, Dickey County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Dickey County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2006 (completed)
  2. Withdrawn / abandonedNov 2011 (project stopped here)
  3. ConsentedNov 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G690
Grid region
MISO (Midcontinent)
Connection point (POI)
Tatakana 230 kV
Location
Dickey County, North Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
16 October 2006
Agreement signed
1 November 2011
Proposed online date
December 2010
Withdrawn
November 2011

Location

Marker shows the centre of Dickey County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Dickey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem