United States › Grid › Interconnection queues › North Dakota

ONSHORE WIND · MISO

Onshore wind project J316, Dickey County

Onshore wind project J316, Dickey County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Dickey County, North Dakota.

Queue statusOperating
  1. PlanningQueued Nov 2013 (completed)
  2. ConsentedAug 2016 (completed)
  3. Construction (completed)
  4. OperatingOct 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J316
Grid region
MISO (Midcontinent)
Connection point (POI)
MDU 230 kV Tatanka-Ellendale line
Location
Dickey County, North Dakota
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
18 November 2013
Agreement signed
30 August 2016
Proposed online date
October 2016
Came online
October 2016

Location

Marker shows the centre of Dickey County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Dickey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem