United States › Grid › Interconnection queues › North Dakota

ONSHORE WIND · MISO

Onshore wind project G359R, Dickey County

Onshore wind project G359R, Dickey County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Dickey County, North Dakota.

Queue statusOperating
  1. PlanningQueued Nov 2015 (completed)
  2. ConsentedMar 2019 (completed)
  3. Construction (completed)
  4. OperatingFeb 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G359R
Grid region
MISO (Midcontinent)
Connection point (POI)
Merricourt Substation
Location
Dickey County, North Dakota
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
GIA
Queue status
Operational
Entered queue
16 November 2015
Agreement signed
20 March 2019
Proposed online date
February 2020
Came online
February 2020

Location

Marker shows the centre of Dickey County; the queue data does not give exact sites.