Onshore wind project J780, Sheridan County

Onshore wind project J780, Sheridan County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Sheridan County, North Dakota, connecting to OTTER TAIL POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J780
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Harvey - Underwood 230kV Line
Location
Sheridan County, North Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 November 2016
Proposed online date
December 2020
Withdrawn
April 2019

Location

Marker shows the centre of Sheridan County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Sheridan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem