ONSHORE WIND Β· MISOOnshore wind project J780, Sheridan County
Onshore wind project J780, Sheridan County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Sheridan County, North Dakota, connecting to OTTER TAIL POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2016 (completed)
- Withdrawn / abandonedApr 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J780
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- OTTER TAIL POWER COMPANY
- Connection point (POI)
- Harvey - Underwood 230kV Line
- Location
- Sheridan County, North Dakota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 14 November 2016
- Proposed online date
- December 2020
- Withdrawn
- April 2019
Location
Marker shows the centre of Sheridan County; the queue data does not give exact sites.