United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
SOLAR Β· MISOSolar project J1622, Sheridan County
Solar project J1622, Sheridan County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Sheridan County, North Dakota, connecting to OTTER TAIL POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedDec 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1622
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- OTTER TAIL POWER COMPANY
- Connection point (POI)
- Harvey-Underwood 230kV
- Location
- Sheridan County, North Dakota
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 23 June 2020
- Proposed online date
- June 2024
- Withdrawn
- December 2022
Location
Marker shows the centre of Sheridan County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Sheridan County
- Onshore wind project J1456, Sheridan CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project J780, Sheridan CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project G951, Sheridan CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Onshore wind project G916, Sheridan CountyOnshore wind Β· 53.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem