United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

SOLAR Β· MISO

Solar project J1622, Sheridan County

Solar project J1622, Sheridan County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Sheridan County, North Dakota, connecting to OTTER TAIL POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1622
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Harvey-Underwood 230kV
Location
Sheridan County, North Dakota
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
23 June 2020
Proposed online date
June 2024
Withdrawn
December 2022

Location

Marker shows the centre of Sheridan County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Sheridan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem