United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
ONSHORE WIND Β· MISOOnshore wind project G916, Sheridan County
Onshore wind project G916, Sheridan County is a 53.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Sheridan County, North Dakota.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2011 (completed)
- Withdrawn / abandonedMay 2014 (project stopped here)
- ConsentedMay 2014 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G916
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- OTP Harvey 230kV Substation
- Location
- Sheridan County, North Dakota
- Technology
- Wind: 53.0 MW
- Total requested
- 53.0 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 28 April 2011
- Agreement signed
- 28 May 2014
- Proposed online date
- October 2010
- Withdrawn
- May 2014
Location
Marker shows the centre of Sheridan County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Sheridan County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem