πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project G916, Sheridan County

Onshore wind project G916, Sheridan County is a 53.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Sheridan County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2011 (completed)
  2. Withdrawn / abandonedMay 2014 (project stopped here)
  3. ConsentedMay 2014 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G916
Grid region
MISO (Midcontinent)
Connection point (POI)
OTP Harvey 230kV Substation
Location
Sheridan County, North Dakota
Technology
Wind: 53.0 MW
Total requested
53.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
28 April 2011
Agreement signed
28 May 2014
Proposed online date
October 2010
Withdrawn
May 2014

Location

Marker shows the centre of Sheridan County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Sheridan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem