United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
ONSHORE WIND Β· MISOOnshore wind project J607, Logan County
Onshore wind project J607, Logan County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Logan County, North Dakota.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedOct 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J607
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Wishek - Heskett 230kV line
- Location
- Logan County, North Dakota
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- GIA
- Queue status
- Withdrawn
- Entered queue
- 9 May 2016
- Proposed online date
- September 2018
- Withdrawn
- October 2018
Location
Marker shows the centre of Logan County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Logan County
- Onshore wind project GI-0804, Logan CountyOnshore wind Β· 672 MW Β· withdrawn
- Onshore wind project GEN-2016-044, Logan CountyOnshore wind Β· 400 MW Β· withdrawn
- Onshore wind project GEN-2023-182, Logan CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GI-0707a, Logan CountyOnshore wind Β· 286 MW Β· withdrawn
- Onshore wind project J3091, Logan CountyOnshore wind Β· 145 MW Β· withdrawn
- Battery storage project GEN-2023-181, Logan CountyBattery storage Β· 100 MW Β· withdrawn
- Onshore wind project GI-0616, Logan CountyOnshore wind Β· 81.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem