ONSHORE WIND Β· MISO

Onshore wind project G757, Adams County

Onshore wind project G757, Adams County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Adams County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2011 (completed)
  2. Withdrawn / abandonedNov 2011 (project stopped here)
  3. ConsentedNov 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G757
Grid region
MISO (Midcontinent)
Connection point (POI)
Gascoyne Generating Station Substation
Location
Adams County, North Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
3 May 2011
Agreement signed
15 November 2011
Proposed online date
June 2009
Withdrawn
November 2011

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Adams County