Onshore wind project GI-0706, Adams County

Onshore wind project GI-0706, Adams County is a 48.0 MW onshore wind request withdrawn in the West interconnection queue, in Adams County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-0706
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Hettinger 230kV
Location
Adams County, North Dakota
Technology
Wind: 48.0 MW
Total requested
48.0 MW
Service type
Energy only (ERIS)
Study phase
IAP
Queue status
Withdrawn
Entered queue
10 April 2007
Proposed online date
December 2009

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem