United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
SOLAR Β· MISOSolar project J1544, Morton County
Solar project J1544, Morton County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Morton County, North Dakota, connecting to MONTANA-DAKOTA UTILITIES CO..
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1544
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MONTANA-DAKOTA UTILITIES CO.
- Connection point (POI)
- Mandan BN-Northwest Mandan 115kV Line
- Location
- Morton County, North Dakota
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 24 June 2020
- Proposed online date
- September 2023
Location
Marker shows the centre of Morton County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Morton County
- Red Butte WindOnshore wind Β· 457 MW Β· in study
- Onshore wind project J2502, Morton CountyOnshore wind Β· 150 MW Β· in study
- Replace 103.1 MW of Heskett Units 1 & 2 with One (1) General Electric synchronous combustion turbine; Heskett 1 & 2Gas Β· 103 MW Β· in study
- Onshore wind project J2157, Morton CountyOnshore wind Β· 100 MW Β· in study
- Onshore wind project J3070, Morton CountyOnshore wind Β· 100 MW Β· in study
- Onshore wind project J2097, Morton CountyOnshore wind Β· 100 MW Β· in study
- Onshore wind project GI-0926, Morton CountyOnshore wind Β· 110 MW Β· built
- Gas project J200, Morton CountyGas Β· 99.0 MW Β· built
- Other project G723, Morton CountyOther Β· 10.0 MW Β· built
- Other project GI-0315, Morton CountyOther Β· 8.0 MW Β· built
- Other project J110, Morton CountyOther Β· 7.5 MW Β· built
- Onshore wind project J1893, Morton CountyOnshore wind Β· 500 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem