United States › Grid › Interconnection queues › North Dakota

ONSHORE WIND · MISO

Onshore wind project J3070, Morton County

Onshore wind project J3070, Morton County is a 100 MW onshore wind request in interconnection study in the MISO interconnection queue, in Morton County, North Dakota.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3070
Grid region
MISO (Midcontinent)
Connection point (POI)
Square Butte 230 kV Substation East
Location
Morton County, North Dakota
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
15 September 2022
Proposed online date
February 2025

Location

Marker shows the centre of Morton County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Morton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem