ONSHORE WIND Β· MISOOnshore wind project H084, Mclean County
Onshore wind project H084, Mclean County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Mclean County, North Dakota.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2008 (completed)
- Withdrawn / abandonedMay 2011 (project stopped here)
- ConsentedMay 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- H084
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- GRE McHenry - Stanton Line 230 kV
- Location
- Mclean County, North Dakota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 3 July 2008
- Agreement signed
- 4 May 2011
- Proposed online date
- December 2010
- Withdrawn
- May 2011
Location
Marker shows the centre of Mclean County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Mclean County
- Onshore wind project GEN-2025-GR3, Mclean CountyOnshore wind Β· 0.0 MW Β· in study
- Coal project G877, Mclean CountyCoal Β· 40.0 MW Β· built
- Coal project G876, Mclean CountyCoal Β· 25.0 MW Β· built
- Other project G119, Mclean CountyOther Β· 750 MW Β· withdrawn
- Onshore wind project MPC02600, Mclean CountyOnshore wind Β· 400 MW Β· withdrawn
- Solar project GEN-2023-031, Mclean CountySolar Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem