United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
ONSHORE WIND Β· MISOOnshore wind project J880, Ward County
Onshore wind project J880, Ward County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Ward County, North Dakota, connecting to NORTHERN STATES POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedOct 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J880
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- Magic City 230kV sub
- Location
- Ward County, North Dakota
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Proposed online date
- September 2020
- Withdrawn
- October 2019
Location
Marker shows the centre of Ward County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Ward County
- Onshore wind project GEN-2017-215, Ward CountyOnshore wind Β· 100 MW Β· agreement signed
- Onshore wind project GEN-2017-214, Ward CountyOnshore wind Β· 100 MW Β· agreement signed
- Battery storage project GEN-2024-327, Ward CountyBattery storage Β· 200 MW Β· in study
- Onshore wind project GEN-2025-GR5, Ward CountyOnshore wind Β· 7.7 MW Β· in study
- Onshore wind project GI-0503, Ward CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project GI-0720, Ward CountyOnshore wind Β· 16.0 MW Β· built
- Onshore wind project GI-0808, Ward CountyOnshore wind Β· 5.0 MW Β· built
- Onshore wind project GI-0113, Ward CountyOnshore wind Β· 3.0 MW Β· built
- Onshore wind project J212, Ward CountyOnshore wind Β· 600 MW Β· withdrawn
- Onshore wind project GI-0905, Ward CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GI-0821, Ward CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project G784, Ward CountyOnshore wind Β· 122 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem