Onshore wind project GI-0720, Ward County

Onshore wind project GI-0720, Ward County is a 16.0 MW onshore wind request built and operating in the West interconnection queue, in Ward County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusOperating
  1. PlanningQueued Nov 2007 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Sep 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-0720
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Developer
PrairieWinds ND1 Inc.
Connection point (POI)
Max-Mallard 115kV
Location
Ward County, North Dakota
Technology
Wind: 16.0 MW
Total requested
16.0 MW
Service type
NRIS and ERIS
Study phase
IAE/IS
Queue status
Operational
Entered queue
5 November 2007
Proposed online date
September 2009

Location

Marker shows the centre of Ward County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Ward County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem