ONSHORE WIND · WEST

Onshore wind project GI-0113, Ward County

Onshore wind project GI-0113, Ward County is a 3.0 MW onshore wind request built and operating in the West interconnection queue, in Ward County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusOperating
  1. PlanningQueued Oct 2001 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-0113
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Mallard 41.8kV
Location
Ward County, North Dakota
Technology
Wind: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
IAE / IS
Queue status
Operational
Entered queue
23 October 2001

Location

Marker shows the centre of Ward County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Ward County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem