Onshore wind project GEN-2025-GR5, Ward County

Onshore wind project GEN-2025-GR5, Ward County is a 7.7 MW onshore wind request in interconnection study in the SPP interconnection queue, in Ward County, North Dakota, connecting to WAPA.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2025-GR5
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Nelson Tap
Location
Ward County, North Dakota
Technology
Wind: 7.7 MW
Total requested
7.7 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
6 October 2025

Location

Marker shows the centre of Ward County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Ward County