United States › Grid › Interconnection queues › North Dakota
BATTERY STORAGE · SPPBattery storage project GEN-2024-327, Ward County
Battery storage project GEN-2024-327, Ward County is a 200 MW battery storage request in interconnection study in the SPP interconnection queue, in Ward County, North Dakota, connecting to CPEC.
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-327
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- CPEC
- Connection point (POI)
- Berthold 115 kV Substation
- Location
- Ward County, North Dakota
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- January 2028
Location
Marker shows the centre of Ward County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Ward County
- Onshore wind project GEN-2017-215, Ward CountyOnshore wind · 100 MW · agreement signed
- Onshore wind project GEN-2017-214, Ward CountyOnshore wind · 100 MW · agreement signed
- Onshore wind project GEN-2025-GR5, Ward CountyOnshore wind · 7.7 MW · in study
- Onshore wind project GI-0503, Ward CountyOnshore wind · 100 MW · built
- Onshore wind project GI-0720, Ward CountyOnshore wind · 16.0 MW · built
- Onshore wind project GI-0808, Ward CountyOnshore wind · 5.0 MW · built
- Onshore wind project GI-0113, Ward CountyOnshore wind · 3.0 MW · built
- Onshore wind project J212, Ward CountyOnshore wind · 600 MW · withdrawn
- Onshore wind project GI-0905, Ward CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J880, Ward CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GI-0821, Ward CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project G784, Ward CountyOnshore wind · 122 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem