United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Texas — page 29
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Cathode BESS Battery storage · CED Development Inc. |
150 MW | In study |
| Photo Solar 1 Solar + storage · CED Development Inc. |
150 MW | In study |
| Solar project GEN-2017-187, Terry County Solar |
150 MW | Agreement signed |
| Cannibal Draw Solar Solar + storage · Cannibal Draw Solar, LLC |
150 MW | Agreement signed |
| Ponferrada Solar Solar · Karol Solar VI |
149 MW | In study |
| Rogers Draw BESS Battery storage · ROGERS DRAW ENERGY STORAGE, LLC |
149 MW | Agreement signed |
| La Casa Wind Onshore wind · LA CASA WIND, LLC |
148 MW | Agreement signed |
| Cosper Solar Solar · Gransolar Texas Twenty LLC |
148 MW | Agreement signed |
| Galaxy Solar Solar + storage · Galaxy Solar, LLC |
148 MW | In study |
| Rain Lily Solar 1 Solar + storage · Rain Lily Solar 1 LLC |
148 MW | In study |
| High Chaparral Solar 138kV Solar · High Chaparral Solar Project, LLC |
148 MW | Paused / redesign |
| John Bull BESS Battery storage · BRP BLUE TOPAZ 13, LLC |
147 MW | In study |
| Chisme Solar Solar + storage · Blue Heron Solar, LLC |
147 MW | In study |
| Neal Solar Solar + storage · CH Neal Solar LLC |
147 MW | In study |
| Dundee West Wind Onshore wind · Felix 2, LLC |
146 MW | Agreement signed |
| Wensowitch Solar Solar · Greenalia Solar Power Wensowitch LLC |
146 MW | In study |
| Chisme Storage Solar + storage · Blue Heron Solar, LLC |
146 MW | In study |
| Moonstone Solar Project Solar · Moon Stone Solar Farm, LLC |
146 MW | Agreement signed |
| Seven Springs Solar Solar + storage · Hancock Springs, LLC |
145 MW | Agreement signed |
| Noria Solar DCC Solar |
145 MW | Paused / redesign |
| Solar project J2165, Liberty County Solar |
145 MW | In study |
| Wang Solar SLF Solar + storage · BT Yixin Solar, LLC |
145 MW | In study |
| Starling Solar Solar + storage · Starling Solar, LLC |
144 MW | Agreement signed |
| Gaia Solar Solar + storage · Gaia Solar, LLC |
144 MW | Agreement signed |
| Starling Solar Solar + storage · Starling Solar, LLC |
144 MW | In study |
| Friendswood Energy Genco Gas · Tejas Power Generation LLC |
144 MW | Agreement signed |
| Rio Star Energy Storage Battery storage · Rio Star Energy Storage, LLC |
144 MW | In study |
| City Breeze BESS Battery storage · City Breeze BESS LLC |
143 MW | Agreement signed |
| Summerhill BESS Battery storage · Taylor ESS, LLC |
143 MW | In study |
| CH Solterra LLC Solar · CH Solterra LLC |
143 MW | In study |
| Gibson Branch BESS Battery storage · Gibson Branch BESS LLC |
143 MW | In study |
| Spindletop Storage Solar + storage · Banita Creek Solar LLC |
143 MW | Agreement signed |
| Cherry Sage Solar 1 SLF Solar + storage · Cherry Sage Solar 1 LLC |
143 MW | In study |
| Solar project GEN-2024-376, Sabine County Solar |
142 MW | In study |
| Monte Alto I Onshore wind · Terra-Gen |
142 MW | Agreement signed |
| Rhoda Storage Battery storage · Milam Energy, LLC |
141 MW | In study |
| Blue Jay Solar Solar · Blue Jay Solar I, LLC |
141 MW | Agreement signed |
| Brizo BESS Battery storage · BRP Brizo BESS LLC |
141 MW | Agreement signed |
| Invictus Energy Storage Battery storage · GSA Land Holdings |
141 MW | In study |
| Battery storage project ERAS-2025-036, Potter County Battery storage |
140 MW | In study |
| Greens Bayou Expansion Gas |
140 MW | Paused / redesign |
| Bonham Solar SLF Solar + storage · J&J Solar Ranch LLC |
138 MW | Agreement signed |
| Demeter Storage 2 Solar + storage · Demeter Solar, LLC |
138 MW | In study |
| Skull Creek Solar Solar · Skull Creek Solar, LLC |
137 MW | Agreement signed |
| Sword Solar Solar + storage · Hidalgo Solar LLC |
137 MW | In study |
| Starr Solar Ranch Solar + storage · Starr Solar Ranch 1 LLC |
137 MW | Agreement signed |
| Turtle Rock Storage Battery storage · Turtle Rock Energy Center, LLC |
136 MW | In study |
| Vial BESS Battery storage · Gransolar Texas Eleven LLC |
135 MW | Agreement signed |
| Stonewall BESS Solar + storage · Stonewall ESS, LLC |
135 MW | In study |
| Pham BESS Battery storage · ASB1, LLC |
133 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)1,976 · 447.2 GW
- SPP (Southwest Power Pool)79 · 20.6 GW
- MISO (Midcontinent)27 · 6,659 MW
- West (non-ISO utilities)12 · 1,947 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)