Requests shown2,094476.4 GW
Active in queue476.4 GW2,094 requests
Agreement signed124.6 GW606 requests
Withdrawn917184.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,094 requests · page 29 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Cathode BESS
Battery storage · CED Development Inc.
150 MWIn study Upton, TXERCOT Aug 2022target 2026
Photo Solar 1
Solar + storage · CED Development Inc.
150 MWIn study Uvalde, TXERCOT Sep 2022target 2027
Solar project GEN-2017-187, Terry County
Solar
150 MWAgreement signed Terry, TXSPP Nov 2017target 2026
Cannibal Draw Solar
Solar + storage · Cannibal Draw Solar, LLC
150 MWAgreement signed Glasscock, TXERCOT Jul 2024target 2028
Ponferrada Solar
Solar · Karol Solar VI
149 MWIn study Navarro, TXERCOT Oct 2024target 2029
Rogers Draw BESS
Battery storage · ROGERS DRAW ENERGY STORAGE, LLC
149 MWAgreement signed Gillespie, TXERCOT Jan 2023target 2026
La Casa Wind
Onshore wind · LA CASA WIND, LLC
148 MWAgreement signed Stephens, TXERCOT Dec 2018target 2026
Cosper Solar
Solar · Gransolar Texas Twenty LLC
148 MWAgreement signed Bell, TXERCOT Jan 2023target 2027
Galaxy Solar
Solar + storage · Galaxy Solar, LLC
148 MWIn study Ellis, TXERCOT Mar 2024target 2028
Rain Lily Solar 1
Solar + storage · Rain Lily Solar 1 LLC
148 MWIn study Hood, TXERCOT Feb 2025target 2028
High Chaparral Solar 138kV
Solar · High Chaparral Solar Project, LLC
148 MWPaused / redesign Brazoria, TXERCOT Jan 2021target 2023
John Bull BESS
Battery storage · BRP BLUE TOPAZ 13, LLC
147 MWIn study Nueces, TXERCOT Jul 2023target 2028
Chisme Solar
Solar + storage · Blue Heron Solar, LLC
147 MWIn study Brown, TXERCOT Jan 2023target 2027
Neal Solar
Solar + storage · CH Neal Solar LLC
147 MWIn study Wharton, TXERCOT May 2025target 2029
Dundee West Wind
Onshore wind · Felix 2, LLC
146 MWAgreement signed Wilbarger, TXERCOT Jan 2023target 2027
Wensowitch Solar
Solar · Greenalia Solar Power Wensowitch LLC
146 MWIn study Navarro, TXERCOT Jan 2022target 2028
Chisme Storage
Solar + storage · Blue Heron Solar, LLC
146 MWIn study Brown, TXERCOT Jan 2023target 2027
Moonstone Solar Project
Solar · Moon Stone Solar Farm, LLC
146 MWAgreement signed Wilson, TXERCOT Oct 2021target 2029
Seven Springs Solar
Solar + storage · Hancock Springs, LLC
145 MWAgreement signed Lampasas, TXERCOT Sep 2023target 2028
Noria Solar DCC
Solar
145 MWPaused / redesign Nueces, TXERCOT Aug 2020target 2025
Solar project J2165, Liberty County
Solar
145 MWIn study Liberty, TXMISO Nov 2021target 2027
Wang Solar SLF
Solar + storage · BT Yixin Solar, LLC
145 MWIn study Falls, TXERCOT Jun 2018target 2026
Starling Solar
Solar + storage · Starling Solar, LLC
144 MWAgreement signed Gonzales, TXERCOT Jun 2020target 2028
Gaia Solar
Solar + storage · Gaia Solar, LLC
144 MWAgreement signed Navarro, TXERCOT Dec 2021target 2026
Starling Solar
Solar + storage · Starling Solar, LLC
144 MWIn study Gonzales, TXERCOT Oct 2022target 2028
Friendswood Energy Genco
Gas · Tejas Power Generation LLC
144 MWAgreement signed Harris, TXERCOT Dec 2022target 2026
Rio Star Energy Storage
Battery storage · Rio Star Energy Storage, LLC
144 MWIn study Wichita, TXERCOT Feb 2025target 2028
City Breeze BESS
Battery storage · City Breeze BESS LLC
143 MWAgreement signed Matagorda, TXERCOT Dec 2022target 2027
Summerhill BESS
Battery storage · Taylor ESS, LLC
143 MWIn study Taylor, TXERCOT Feb 2025target 2028
CH Solterra LLC
Solar · CH Solterra LLC
143 MWIn study Hopkins, TXERCOT Mar 2021target 2026
Gibson Branch BESS
Battery storage · Gibson Branch BESS LLC
143 MWIn study Lampasas, TXERCOT May 2024target 2028
Spindletop Storage
Solar + storage · Banita Creek Solar LLC
143 MWAgreement signed Nacogdoches, TXERCOT Jul 2024target 2027
Cherry Sage Solar 1 SLF
Solar + storage · Cherry Sage Solar 1 LLC
143 MWIn study Concho, TXERCOT Apr 2025target 2029
Solar project GEN-2024-376, Sabine County
Solar
142 MWIn study Sabine, TXSPP Mar 2025target 2028
Monte Alto I
Onshore wind · Terra-Gen
142 MWAgreement signed Willacy, TXERCOT Nov 2016target 2028
Rhoda Storage
Battery storage · Milam Energy, LLC
141 MWIn study Milam, TXERCOT Apr 2022target 2028
Blue Jay Solar
Solar · Blue Jay Solar I, LLC
141 MWAgreement signed Grimes, TXERCOT May 2017target 2025
Brizo BESS
Battery storage · BRP Brizo BESS LLC
141 MWAgreement signed Victoria, TXERCOT Oct 2021target 2027
Invictus Energy Storage
Battery storage · GSA Land Holdings
141 MWIn study Coleman, TXERCOT Jan 2024target 2028
Battery storage project ERAS-2025-036, Potter County
Battery storage
140 MWIn study Potter, TXSPP Oct 2025target 2029
Greens Bayou Expansion
Gas
140 MWPaused / redesign Harris, TXERCOT Apr 2019
Bonham Solar SLF
Solar + storage · J&J Solar Ranch LLC
138 MWAgreement signed Limestone, TXERCOT Nov 2022target 2027
Demeter Storage 2
Solar + storage · Demeter Solar, LLC
138 MWIn study Caldwell, TXERCOT Oct 2024target 2029
Skull Creek Solar
Solar · Skull Creek Solar, LLC
137 MWAgreement signed Anderson, TXERCOT May 2021target 2027
Sword Solar
Solar + storage · Hidalgo Solar LLC
137 MWIn study Starr, TXERCOT Mar 2024target 2029
Starr Solar Ranch
Solar + storage · Starr Solar Ranch 1 LLC
137 MWAgreement signed Starr, TXERCOT Nov 2018target 2025
Turtle Rock Storage
Battery storage · Turtle Rock Energy Center, LLC
136 MWIn study Freestone, TXERCOT May 2024target 2028
Vial BESS
Battery storage · Gransolar Texas Eleven LLC
135 MWAgreement signed Hill, TXERCOT Jul 2022target 2027
Stonewall BESS
Solar + storage · Stonewall ESS, LLC
135 MWIn study Stonewall, TXERCOT Feb 2025target 2028
Pham BESS
Battery storage · ASB1, LLC
133 MWIn study Anderson, TXERCOT Jun 2024target 2028
Page 29 of 42

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)