United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTStarling Solar
Starling Solar is a 144 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Gonzales County, Texas.
Queue statusIn planning
- PlanningQueued Oct 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 24INR0440
- Grid region
- ERCOT (Texas)
- Developer
- Starling Solar, LLC
- Connection point (POI)
- 138-kV Birdhouse (7255) Starling Solar Phase II is a an addition of 42.24MW to the 23INR0035 (solar) filed in 2020. 23INR0181 (storage) was filed in 2021.
- Location
- Gonzales County, Texas
- Technology
- Solar: 144 MW · Battery
- Total requested
- 144 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 6 October 2022
- Proposed online date
- January 2028
Location
Marker shows the centre of Gonzales County; the queue data does not give exact sites.
Other requests in Gonzales County
- Starling SolarSolar + storage · 144 MW · agreement signed
- Rocinante SolarSolar + storage · 95.3 MW · agreement signed
- Starling StorageSolar + storage · 63.6 MW · agreement signed
- Rocinante BESSSolar + storage · 33.2 MW · agreement signed
- Columbine WindOnshore wind · 295 MW · in study
- Nockenut Springs Solar 3Solar · 201 MW · in study
- Nockenut Springs Solar 5Solar · 201 MW · in study
- Nockenut Springs Solar 4Solar · 201 MW · in study
- Beeman BESSBattery storage · 50.2 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem