SOLAR · ERCOT

Nockenut Springs Solar 4

Nockenut Springs Solar 4 is a 201 MW solar request in interconnection study in the ERCOT interconnection queue, in Gonzales County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0193
Grid region
ERCOT (Texas)
Developer
Pecan Springs Energy, LLC
Connection point (POI)
The 345 kV Elm Creek - South Texas Project Line (Bus #5133 - #5915)
Location
Gonzales County, Texas
Technology
Solar: 201 MW
Total requested
201 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
15 September 2022
Proposed online date
June 2029

Location

Marker shows the centre of Gonzales County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Gonzales County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem