SOLAR + STORAGE · ERCOT

Starling Storage

Starling Storage is a 63.6 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Gonzales County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2021 (completed)
  2. ConsentedAug 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0181
Grid region
ERCOT (Texas)
Developer
Starling Storage, LLC
Connection point (POI)
tap 138kV 7224 Luling - 7245 Gonzales
Location
Gonzales County, Texas
Technology
Battery: 63.6 MW · Battery
Total requested
63.6 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
25 January 2021
Agreement signed
3 August 2023
Proposed online date
May 2027

Location

Marker shows the centre of Gonzales County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Gonzales County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem