🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas — page 20

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,094476.4 GW
Active in queue476.4 GW2,094 requests
Agreement signed124.6 GW606 requests
Withdrawn917184.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,094 requests · page 20 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Dodd Solar I
Solar · Forest Grove Solar LLC
202 MWAgreement signed Henderson, TXERCOT Jun 2021target 2028
Donegal Solar
Solar · HE-Cottonwood Solar LLC
202 MWAgreement signed Dickens, TXERCOT Oct 2020target 2028
Soda Lake Solar 2 SLF
Solar + storage · Crane II Solar Electric, LLC
202 MWAgreement signed Crane, TXERCOT Sep 2020target 2027
Avant Prairie BESS
Battery storage · Avant Prairie ESS LLC
202 MWIn study Freestone, TXERCOT Sep 2024target 2027
Mitchell Plant Road Storage
Battery storage
202 MWPaused / redesign Pecos, TXERCOT Feb 2022
Spurland Solar II
Solar · Spurland Solar II
202 MWIn study Dickens, TXERCOT Nov 2025target 2028
Texas Cotton Solar
Solar · RWE Solar Development, LLC
202 MWIn study Brazos, TXERCOT Oct 2024target 2028
Goldeneye BESS
Battery storage · Black Mountain Energy Storage II
202 MWAgreement signed Bell, TXERCOT Jun 2022target 2028
Stoneridge Solar
Solar · Stoneridge Solar, LLC
202 MWAgreement signed Milam, TXERCOT Oct 2021target 2026
Mesteno Wind
Onshore wind · Mesteno Windpower, LLC
202 MWAgreement signed Starr, TXERCOT Dec 2014target 2025
OCI Cobb Creek ESS
Solar + storage · Hillsboro Solar Project LLC
202 MWAgreement signed Hill, TXERCOT Dec 2022target 2027
Cattleman Wind A
Onshore wind · RWE Renewables Development, LLC
202 MWPaused / redesign Castro, TXERCOT Sep 2013target 2021
Cattleman Wind B
Onshore wind · RWE Renewables Development, LLC
202 MWPaused / redesign Castro, TXERCOT Sep 2013target 2021
Mitchell Plant Road Solar
Solar
202 MWPaused / redesign Pecos, TXERCOT Feb 2022target 2025
Thomas Cameron BESS
Battery storage · Thomas Cameron BESS LLC
202 MWAgreement signed Lampasas, TXERCOT Jun 2023target 2027
Sun Angel ESS
Battery storage · Sun Angel ESS LLC
202 MWIn study Angelina, TXERCOT Jun 2024target 2028
Corvus Solar
Solar · Corvus Solar, LLC
202 MWAgreement signed Webb, TXERCOT Feb 2024target 2028
Soluce Cotton Storage
Solar + storage · CTPB1,LLC
202 MWIn study Cottle, TXERCOT Feb 2025target 2028
Tri-X Solar 1 SLF
Solar + storage · Crane I Solar Electric, LLC
202 MWAgreement signed Crane, TXERCOT Nov 2016target 2027
Tex-Bar ESS
Battery storage · Tex-Bar ESS LLC
202 MWIn study Madison, TXERCOT Mar 2024target 2027
Padua Grid BESS Unit 3
Battery storage · Padua Grid 3, LLC
201 MWAgreement signed Bexar, TXERCOT Mar 2024target 2026
Exodus BESS
Battery storage · Exodus Solar LLC
201 MWIn study Caldwell, TXERCOT Jul 2023target 2027
Sawtooth Solar
Solar · Sawtooth Solar, LLC
201 MWIn study Runnels, TXERCOT Nov 2025target 2030
Padrino Solar
Solar · Hill Solar II, LLC
201 MWAgreement signed Hill, TXERCOT Sep 2022target 2026
Nockenut Springs Solar 3
Solar · Pecan Springs Energy, LLC
201 MWIn study Gonzales, TXERCOT Sep 2020target 2029
Desert Palm BESS
Battery storage · Desert Palm BESS LLC
201 MWIn study Dimmit, TXERCOT Aug 2024target 2027
El Molino Solar SLF
Solar + storage · El Molino Solar, LLC
201 MWIn study Webb, TXERCOT Jan 2023target 2027
Caladium BESS
Battery storage · Caladium Storage, LLC
201 MWIn study Waller, TXERCOT Nov 2024target 2027
Snap Jaw BESS
Other · Moccasin Pointe Grid, LLC
201 MWPaused / redesign Harris, TXERCOT Apr 2021target 2028
Finch Storage
Battery storage · Finch Storage, LLC
201 MWIn study Mclennan, TXERCOT Jun 2025target 2028
Tucana BESS
Battery storage · BRP Tucana BESS LLC
201 MWIn study Andrews, TXERCOT Jun 2021target 2028
Rush ESS
Battery storage · OCI Solar Power LLC
201 MWIn study Bexar, TXERCOT Nov 2023target 2027
Eldora BESS
Solar + storage · Eldora Energy LLC
201 MWAgreement signed Matagorda, TXERCOT Jun 2022target 2028
Nockenut Springs Solar 5
Solar · Pecan Springs Energy, LLC
201 MWIn study Gonzales, TXERCOT Feb 2023target 2029
Nockenut Springs Solar 4
Solar · Pecan Springs Energy, LLC
201 MWIn study Gonzales, TXERCOT Sep 2022target 2029
Echols Grove, LLC
Solar · Echols Grove, LLC
201 MWAgreement signed Lamar, TXERCOT Apr 2023target 2027
Savannah Oaks Solar
Solar · Savannah Oaks Solar Project LLC
201 MWIn study Madison, TXERCOT Jan 2023target 2028
Wintergarden BESS
Battery storage · Wintergarden BESS LLC
201 MWIn study Dimmit, TXERCOT Aug 2024target 2028
Spinosa BESS
Battery storage · Spinosa Energy Center, LLC
201 MWIn study Wichita, TXERCOT Apr 2025target 2028
Outer Loop BESS
Battery storage · Black Mountain Energy Storage II
201 MWIn study Harris, TXERCOT Sep 2021target 2027
Apache Hill BESS
Battery storage · APACHE HILL ENERGY CENTER
201 MWAgreement signed Hood, TXERCOT Nov 2022target 2026
Seragio BESS
Battery storage · Seragio BESS, LLC
201 MWIn study Ector, TXERCOT Sep 2022target 2027
BRP Pictor BESS
Battery storage · BRP Pictor BESS LLC
201 MWIn study Crane, TXERCOT Jul 2020target 2025
Morrow Lake Storage
Solar + storage · Morrow Lake Storage, LLC
201 MWIn study Frio, TXERCOT Feb 2020target 2026
Pine Forest BESS 2
Battery storage
201 MWPaused / redesign Hopkins, TXERCOT Dec 2024
Dry Creek Solar I
Solar · OAK HILL SOLAR LLC
201 MWAgreement signed Rusk, TXERCOT Aug 2021target 2026
Motif BESS II
Battery storage · Motif Storage, LLC
201 MWIn study Bandera, TXERCOT Nov 2024target 2029
Jasper BESS
Battery storage · Jasper BESS, LLC
201 MWIn study Midland, TXERCOT Sep 2022target 2028
Ramsey Storage
Battery storage · Hecate Energy Ramsey Storage LLC
201 MWAgreement signed Wharton, TXERCOT May 2020target 2027
Blue Heron BESS
Battery storage · Blue Heron BESS, LLC
201 MWIn study Reeves, TXERCOT Oct 2022target 2028
Page 20 of 42

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)