🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Finch Storage

Finch Storage is a 201 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Mclennan County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0363
Grid region
ERCOT (Texas)
Developer
Finch Storage, LLC
Connection point (POI)
165 WINDSORSW 138kV
Location
Mclennan County, Texas
Technology
Battery: 201 MW
Total requested
201 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
5 June 2025
Proposed online date
September 2028

Location

Marker shows the centre of Mclennan County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Mclennan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem