Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5212.1 GW
Active in queue1,797 MW5 requests
Agreement signed405 MW2 requests
Withdrawn5212.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

52 requests · page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Rockwood G
Gas · Lincoln Clean
1,122 MWWithdrawn / abandoned ERCOT Apr 2014target 2019
Shawnee G
Gas · Lincoln Clean
928 MWWithdrawn / abandoned ERCOT Jul 2014target 2019
Eagle Mountain SES
Gas · Luminant
853 MWWithdrawn / abandoned ERCOT Jul 2014target 2019
Site C Brazos G
Gas · Brazos Elec Coop
800 MWWithdrawn / abandoned ERCOT Apr 2014target 2021
Union Valley G
Gas · Quantum
592 MWWithdrawn / abandoned ERCOT May 2014target 2019
Clear Springs G
Gas · Quantum
592 MWWithdrawn / abandoned ERCOT May 2014target 2019
Van Alstyne G
Gas · Navasota
548 MWWithdrawn / abandoned ERCOT May 2014target 2018
Halyard Henderson
Gas · Halyard Energy
484 MWWithdrawn / abandoned Henderson, TXERCOT Mar 2014target 2021
Lake Creek 3 G
Gas · Luminant
471 MWWithdrawn / abandoned ERCOT Jun 2014target 2018
Tradinghouse G
Gas · Luminant
471 MWWithdrawn / abandoned ERCOT Mar 2014target 2018
Pullman Road Wind
Onshore wind · SunEdison
300 MWWithdrawn / abandoned ERCOT Feb 2014target 2019
Pumpkin Farm Wind
Onshore wind · Apex Clean
281 MWWithdrawn / abandoned Floyd, TXERCOT Feb 2014target 2020
Pecan Creek 1 Gas
Gas · NTE Energy
280 MWWithdrawn / abandoned ERCOT Feb 2014target 2019
RE Maplewood 2c Solar
Solar · Recurrent Energy
250 MWWithdrawn / abandoned Pecos, TXERCOT Oct 2014target 2021
San Roman Wind 2
Onshore wind · Pioneer Green
201 MWWithdrawn / abandoned ERCOT Dec 2014target 2016
Red River Saltfork W
Onshore wind · Chermac
201 MWWithdrawn / abandoned ERCOT Jan 2014target 2017
Watusi Wind, LLC
Onshore wind · NextEra Energy Resources
201 MWWithdrawn / abandoned ERCOT Jan 2014target 2016
WIT Ranch Wind
Onshore wind · Eon
200 MWWithdrawn / abandoned ERCOT Sep 2014target 2019
Buffalo Wind 2
Onshore wind · National Renewable Solutions
199 MWWithdrawn / abandoned ERCOT Jan 2014target 2017
Horseshoe Bend S
Solar · Luminant
150 MWWithdrawn / abandoned ERCOT Sep 2014target 2017
Solar Prime TX-10
Solar · Solar Prime
150 MWWithdrawn / abandoned ERCOT Jul 2014target 2016
King Mt II
Solar · Nextera
150 MWWithdrawn / abandoned ERCOT Sep 2014target 2016
Clear Water Solar
Solar · Hilliard Energy
150 MWWithdrawn / abandoned ERCOT Nov 2014target 2016
Chocolate Bayou Wind
Onshore wind · Engie
150 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2014target 2022
TXP Ricebird
Gas · TXP Holdings
142 MWWithdrawn / abandoned ERCOT Jan 2014target 2018
Barilla Solar 3
Solar · First Solar
140 MWWithdrawn / abandoned ERCOT Mar 2014target 2019
Bosque Upgrade
Gas · Calpine
124 MWWithdrawn / abandoned ERCOT Feb 2014target 2019
SP-TX-08
Solar · Solar Prime
120 MWWithdrawn / abandoned ERCOT Jun 2014target 2016
RE Avalon Solar
Solar · Recurrent Energy
105 MWWithdrawn / abandoned ERCOT Mar 2014target 2017
BNB Lamesa Solar 2
Solar · BNB
100 MWWithdrawn / abandoned ERCOT Jun 2014target 2016
Braford Wind
Onshore wind · Nextera
100 MWWithdrawn / abandoned ERCOT Jan 2014target 2016
RE Maplewood 2e Solar
Solar · Recurrent Energy
100 MWWithdrawn / abandoned Pecos, TXERCOT Oct 2014target 2020
RE Monument Solar
Solar · Recurrent Energy
100 MWWithdrawn / abandoned ERCOT Mar 2014target 2017
New Falcon Wind
Onshore wind · Nextera
100 MWWithdrawn / abandoned ERCOT Jan 2014target 2016
Jobe Solar
Solar · Sun Power
100 MWWithdrawn / abandoned ERCOT Dec 2014target 2017
Locust Solar
Solar · SunEdison
100 MWWithdrawn / abandoned ERCOT Oct 2014target 2020
Dogwood Solar
Solar · SunEdison
100 MWWithdrawn / abandoned ERCOT Oct 2014target 2020
Briscoe Solar
Solar · Juwi Solar
100 MWWithdrawn / abandoned ERCOT Aug 2014target 2016
Caballo Solar
Solar · Recurrent Energy
100 MWWithdrawn / abandoned ERCOT Mar 2014target 2018
RE Maplewood 2d Solar
Solar · Recurrent Energy
100 MWWithdrawn / abandoned Pecos, TXERCOT Oct 2014target 2020
RE Palmwood 1 Solar
Solar · Recurrent Energy
98.0 MWWithdrawn / abandoned ERCOT Sep 2014target 2017
Parker Ranch Solar 1
Solar · SunPower
88.0 MWWithdrawn / abandoned ERCOT Aug 2014target 2018
Corpus Christi Upgrade
Gas · Calpine
82.0 MWWithdrawn / abandoned ERCOT Feb 2014target 2019
Mason Mt Wind
Onshore wind · Enel Green
62.0 MWWithdrawn / abandoned ERCOT Apr 2014target 2019
Parker Ranch Solar 2
Solar · SunPower
56.0 MWWithdrawn / abandoned ERCOT Dec 2014target 2018
M&G Resins Corpus Christi
Gas · M&G Resins USA, LLC
51.0 MWWithdrawn / abandoned ERCOT Jan 2014target 2015
BThorn
Solar · SunEdison
50.0 MWWithdrawn / abandoned ERCOT Nov 2014target 2020
SolaireHolman 2
Solar · Solaire Direct
50.0 MWWithdrawn / abandoned ERCOT Jun 2014target 2016
SP-TX-09
Solar · Solar Prime
45.0 MWWithdrawn / abandoned ERCOT Jul 2014target 2016
Castle Gap Solar 2
Solar · Solar Prime
30.0 MWWithdrawn / abandoned ERCOT Sep 2014target 2020
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)