United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

King Mt II

King Mt II is a 150 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2014 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
16INR0060
Grid region
ERCOT (Texas)
Developer
Nextera
Connection point (POI)
130932 King SE 138kV
Technology
Solar: 150 MW
Total requested
150 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
9 September 2014
Proposed online date
December 2016

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem