Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown589109.2 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

589 requests · page 9 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 132, Hampton County
Solar
75.0 MWIn study Hampton, SCSoutheast Dec 2019target 2024
Solar project 259, Highlands County
Solar · Placid Solar II, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Solar project 258, Highlands County
Solar · Placid Solar, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Solar project 273, Polk County
Solar · FL Solar 10, LLC
74.9 MWUnder construction Polk, FLSoutheast Dec 2019target 2022
Solar project 269, Marion County
Solar · Solar FL 2018 LLC
74.9 MWIn study Marion, FLSoutheast Sep 2019target 2021
Solar project 376, Baker County
Solar · FPL
74.5 MWIn study Baker, FLSoutheast Nov 2019target 2027
Solar project 124, Aiken County
Solar
74.0 MWUnder construction Aiken, SCSoutheast Feb 2019target 2025
Harmony Plains Solar and Storage Facility
Solar + storage
70.0 MWAgreement signed Warren, NJPJM Oct 2019target 2026
Dixon Solar
Solar
70.0 MWAgreement signed Jackson, OHPJM Dec 2019target 2028
Granite Hill Solar
Solar
70.0 MWPaused / redesign Adams, PAPJM Mar 2019target 2026
Solar project 388, Simpson County
Solar
69.0 MWAgreement signed Simpson, KYSoutheast Aug 2019target 2025
Solar + storage project J1202, Randolph County
Solar + storage
68.4 MWAgreement signed Randolph, ILMISO Apr 2019target 2024
Morrow County Solar II
Solar
64.0 MWPaused / redesign Morrow, OHPJM Sep 2019target 2026
Mt Olive Creek Solar
Solar
60.0 MWAgreement signed Russell, KYPJM Jun 2019target 2026
Mark Center Solar Project
Solar
60.0 MWAgreement signed Defiance, OHPJM Mar 2019target 2026
Albemarle Beach Solar
Solar
60.0 MWAgreement signed Washington, NCPJM Jan 2019target 2026
Horseshoe Bend Solar
Solar
60.0 MWAgreement signed Green, KYPJM Jul 2019target 2026
Hydro project J1213, Iron County
Hydro
60.0 MWAgreement signed Iron, MOMISO Apr 2019target 2024
Solar project J1387, Jasper County
Solar
60.0 MWAgreement signed Jasper, INMISO Apr 2019target 2024
Pigeon Run Solar and Storage
Solar · Pigeon Run Solar, LLC
60.0 MWAgreement signed Campbell, VAPJM Mar 2019target 2031
Luyster Creek Energy Storage 1
Battery storage · Eastern Generation, LLC
57.3 MWIn study Queens, NYNYISO May 2019target 2027
Dover Solar Facility
Solar
55.0 MWPaused / redesign Whitley, INPJM Mar 2019target 2026
Hardin Energy Center – Storage II
Battery storage
55.0 MWPaused / redesign Hardin, OHPJM Mar 2019target 2026
Flat Run Solar
Solar
55.0 MWAgreement signed Barren, KYPJM Aug 2019target 2026
Dover Solar
Solar
55.0 MWPaused / redesign York, PAPJM Mar 2019target 2026
Gladys Solar
Solar · Gladys Solar, LLC
53.0 MWAgreement signed Campbell, VAPJM Mar 2019target 2031
Solar project QF19-081, Jefferson County
Solar
53.0 MWAgreement signed Jefferson, ORWest Nov 2019target 2022
Mars Solar
Solar
52.8 MWPaused / redesign Childress, TXERCOT Feb 2019
Wythe County Solar Project
Battery storage
52.2 MWAgreement signed Wythe, VAPJM Mar 2019target 2027
Clermont County Solar Project
Battery storage
52.2 MWPaused / redesign Clermont, OHPJM Jun 2019target 2025
Gas project GI-78, Mayes County
Gas
52.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2020
Solar + storage project J1198, Jasper County
Solar + storage
51.8 MWAgreement signed Jasper, ILMISO Apr 2019target 2023
Ryan Energy Storage
Battery storage · Ryan Storage LLC
51.6 MWAgreement signed Coryell, TXERCOT Jan 2019target 2026
Hawks Nest Hydro
Hydro
51.0 MWAgreement signed Fayette, WVPJM Mar 2019target 2028
Ventasso Energy Storage
Battery storage
50.8 MWAgreement signed San Diego, CACAISO Apr 2019target 2026
Volunteer Storage
Battery storage · Blackjack Storage LLC
50.6 MWIn study Caldwell, TXERCOT Jan 2019target 2028
Pearl Crescent Storage
Solar + storage · RWE Solar Development, LLC
50.3 MWIn study Colorado, TXERCOT Dec 2019target 2026
Voyager Storage
Battery storage · EDF Renewables Development, Inc.
50.1 MWIn study Wharton, TXERCOT Jan 2019target 2028
Tokyo TxHSR TPSS EW-1
Other · Texas Central Rail Holdings, LLC
50.0 MWIn study Ellis, TXERCOT Jan 2019target 2028
Gas project GI-77, Mayes County
Gas
50.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2019
MC Solar I
Solar
50.0 MWAgreement signed Mercer, PAPJM Mar 2019target 2027
Zion Energy Center - BESS
Battery storage
50.0 MWAgreement signed Lake, ILPJM Nov 2019target 2027
Edgewater Storage
Battery storage · Edgewater Battery Storage LLC
50.0 MWIn study Ellis, TXERCOT Apr 2019target 2028
Battery storage project Company JV, Carson City County
Battery storage
50.0 MWAgreement signed Carson City, NVWest Mar 2019target 2023
Juliet Energy
Solar
50.0 MWAgreement signed Wood, OHPJM Jul 2019target 2026
Battery storage project J1477, Scott County
Battery storage
50.0 MWAgreement signed Scott, IAMISO Apr 2019target 2024
Atlanta TxHSR TPSS DS-1
Other · Texas Central Rail Holdings, LLC
50.0 MWIn study Dallas, TXERCOT Jan 2019target 2028
Battery storage project Q315, Coconino County
Battery storage
50.0 MWPaused / redesign Coconino, AZWest Sep 2019target 2022
South Orchard
Battery storage · Garden Reserve Energy, LLC
50.0 MWAgreement signed Cumberland, NJPJM Sep 2019target 2028
Battery storage project J1229, Muscatine County
Battery storage
50.0 MWAgreement signed Muscatine, IAMISO Apr 2019target 2026
Page 9 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)