United States › Grid › Interconnection queues › Pennsylvania

SOLAR · PJM

MC Solar I

MC Solar I is a 50.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Mercer County, Pennsylvania, connecting to ATSI.

Queue statusConsented
  1. PlanningQueued Mar 2019 (completed)
  2. ConsentedJul 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AE2-285
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Maysville 69 kV
Location
Mercer County, Pennsylvania
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
30 March 2019
Agreement signed
14 July 2021
Proposed online date
January 2027

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem