United States › Grid › Interconnection queues › Pennsylvania
SOLAR · PJMJackson Center Solar Facility
Jackson Center Solar Facility is a 20.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Mercer County, Pennsylvania, connecting to ATSI.
Queue statusConsented
- PlanningQueued Sep 2018 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AE1-183
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Maysville-McDowell 69 kV
- Location
- Mercer County, Pennsylvania
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 26 September 2018
- Proposed online date
- July 2026
Location
Marker shows the centre of Mercer County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Mercer County
- MC Solar ISolar · 50.0 MW · agreement signed
- Jackson Center Solar IISolar · 20.0 MW · agreement signed
- Welcome Solar, LLCSolar + storage · 19.9 MW · agreement signed
- Other project AI1-053, Mercer CountyOther · 6.6 MW · in study
- Solar project AI2-467, Mercer CountySolar · 5.8 MW · in study
- Solar project AI2-469, Mercer CountySolar · 5.8 MW · in study
- Solar project AI2-470, Mercer CountySolar · 5.8 MW · in study
- Solar project AH2-023, Mercer CountySolar · 5.0 MW · in study
- Solar + storage project AH2-181, Mercer CountySolar + storage · 3.0 MW · in study
- Solar + storage project AG1-490, Mercer CountySolar + storage · 125 MW · withdrawn
- Solar project AE2-193, Mercer CountySolar · 120 MW · withdrawn
- Solar project AD2-120, Mercer CountySolar · 120 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem