United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Edgewater Storage

Edgewater Storage is a 50.0 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Ellis County, Texas.

Queue statusIn planning
  1. PlanningQueued Apr 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
21INR0280
Grid region
ERCOT (Texas)
Developer
Edgewater Battery Storage LLC
Connection point (POI)
210 Reagor Springs 69kV
Location
Ellis County, Texas
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
8 April 2019
Proposed online date
February 2028

Location

Marker shows the centre of Ellis County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Ellis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem