Solar project 132, Hampton County

Solar project 132, Hampton County is a 75.0 MW solar request in interconnection study in the Southeast interconnection queue, in Hampton County, South Carolina, connecting to Santee Cooper.

Queue statusIn planning
  1. PlanningQueued Dec 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
132
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Santee Cooper
Location
Hampton County, South Carolina
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
2022 Trans Cluster
Queue status
Active
Entered queue
20 December 2019
Proposed online date
May 2024

Location

Marker shows the centre of Hampton County; the queue data does not give exact sites.

Power plants in South Carolina · Transmission lines in South Carolina

Other requests in Hampton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem