United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTRyan Energy Storage
Ryan Energy Storage is a 51.6 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Coryell County, Texas.
Queue statusConsented
- PlanningQueued Jan 2019 (completed)
- ConsentedFeb 2021 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 20INR0246
- Grid region
- ERCOT (Texas)
- Developer
- Ryan Storage LLC
- Connection point (POI)
- 37580 TNPancake 69kV
- Location
- Coryell County, Texas
- Technology
- Battery: 51.6 MW
- Total requested
- 51.6 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 15 January 2019
- Agreement signed
- 18 February 2021
- Proposed online date
- December 2026
Location
Marker shows the centre of Coryell County; the queue data does not give exact sites.
Other requests in Coryell County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem