United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTBynum Solar Project
Bynum Solar Project is a 56.0 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Coryell County, Texas.
Queue statusConsented
- PlanningQueued Dec 2021 (completed)
- ConsentedNov 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 24INR0181
- Grid region
- ERCOT (Texas)
- Developer
- Bynum Solar Project, LLC
- Connection point (POI)
- Tap 69kV 37470 Olsen - 37520 Sycamore
- Location
- Coryell County, Texas
- Technology
- Solar: 56.0 MW
- Total requested
- 56.0 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 18 December 2021
- Agreement signed
- 22 November 2023
- Proposed online date
- February 2026
Location
Marker shows the centre of Coryell County; the queue data does not give exact sites.
Other requests in Coryell County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem