Withdrawn queue requests in Wisconsin — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24049.1 GW
Active in queue26.6 GW117 requests
Agreement signed3,635 MW26 requests
Withdrawn24049.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

240 requests · page 5 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G953, Grant County
Onshore wind
50.0 MWWithdrawn / abandoned Grant, WIMISO Jan 2008target 2011
Onshore wind project J217, Columbia County
Onshore wind
50.0 MWWithdrawn / abandoned Columbia, WIMISO Jun 2011target 2014
Solar + storage project J2834, Fond Du Lac County
Solar + storage
50.0 MWWithdrawn / abandoned Fond Du Lac, WIMISO Sep 2022target 2025
Other project J040, Marathon County
Other
50.0 MWWithdrawn / abandoned Marathon, WIMISO Mar 20092013
Onshore wind project J084, Grant County
Onshore wind
50.0 MWWithdrawn / abandoned Grant, WIMISO Oct 2009target 2012
Onshore wind project G691, Vernon County
Onshore wind
50.0 MWWithdrawn / abandoned Vernon, WIMISO Oct 2006target 2007
Onshore wind project G421, Brown County
Onshore wind
50.0 MWWithdrawn / abandoned Brown, WIMISO Mar 2004target 2005
Onshore wind project G483, Green County
Onshore wind
50.0 MWWithdrawn / abandoned Green, WIMISO Nov 2004target 2005
Battery storage project J2439, Marathon County
Battery storage
50.0 MWWithdrawn / abandoned Marathon, WIMISO Sep 2022target 2028
Onshore wind project G749, Lafayette County
Onshore wind
50.0 MWWithdrawn / abandoned Lafayette, WIMISO Feb 2007target 2010
Solar + storage project J2293, Adams County
Solar + storage
50.0 MWWithdrawn / abandoned Adams, WIMISO Nov 2021target 2025
Solar project J1127, Green County
Solar
49.9 MWWithdrawn / abandoned Green, WIMISO Mar 2018target 2021
Solar project J2021, Trempealeau County
Solar
48.4 MWWithdrawn / abandoned Trempealeau, WIMISO Jul 2021target 2025
Onshore wind project H024, Columbia County
Onshore wind
48.0 MWWithdrawn / abandoned Columbia, WIMISO May 2008target 2012
Battery storage project J1971, Dane County
Battery storage
45.0 MWWithdrawn / abandoned Dane, WIMISO Nov 2021target 2025
Solar project J1569, Pierce County
Solar
44.0 MWWithdrawn / abandoned Pierce, WIMISO Jun 2020target 2023
Onshore wind project J807, Lafayette County
Onshore wind
41.4 MWWithdrawn / abandoned Lafayette, WIMISO Jun 2017target 2021
Solar + storage project J2833, Wood County
Solar + storage
40.0 MWWithdrawn / abandoned Wood, WIMISO Sep 2022target 2025
Battery storage project J1954, Walworth County
Battery storage
35.0 MWWithdrawn / abandoned Walworth, WIMISO Aug 2021target 2025
Onshore wind project H036, Columbia County
Onshore wind
30.0 MWWithdrawn / abandoned Columbia, WIMISO May 2008target 2011
Onshore wind project J079, Columbia County
Onshore wind
29.0 MWWithdrawn / abandoned Columbia, WIMISO Oct 2009target 2012
Coal project J269, Columbia County
Coal
26.0 MWWithdrawn / abandoned Columbia, WIMISO Jan 2013target 2014
Battery storage project J1983, Dane County
Battery storage
25.0 MWWithdrawn / abandoned Dane, WIMISO Nov 2021target 2025
Battery storage project J1345, Dodge County
Battery storage
25.0 MWWithdrawn / abandoned Dodge, WIMISO Apr 2019target 2021
Solar project J1397, Juneau County
Solar
25.0 MWWithdrawn / abandoned Juneau, WIMISO Apr 2019target 2022
Other project G415, Waupaca County
Other
25.0 MWWithdrawn / abandoned Waupaca, WIMISO Mar 2004target 2005
Battery storage project J1429, Juneau County
Battery storage
24.0 MWWithdrawn / abandoned Juneau, WIMISO Apr 2019target 2022
Other project G832, Chippewa County
Other
20.0 MWWithdrawn / abandoned Chippewa, WIMISO Aug 2007target 2010
Battery storage project J1101, Manitowoc County
Battery storage
20.0 MWWithdrawn / abandoned Manitowoc, WIMISO Mar 2018target 2023
Onshore wind project G423, Columbia County
Onshore wind
19.0 MWWithdrawn / abandoned Columbia, WIMISO Apr 2004target 2006
Gas project J1843, Dane County
Gas
12.0 MWWithdrawn / abandoned Dane, WIMISO Jan 2022target 2023
Replace 11.4 of WPS.LAKEFRN96 Unit with natural gas (with diesel as a backup); Lakefront 9
Gas
11.4 MWWithdrawn / abandoned Manitowoc, WIMISO Jul 2020target 2022
Nuclear project G391, Kewaunee County
Nuclear
10.0 MWWithdrawn / abandoned Kewaunee, WIMISO Jan 2004target 2004
Other project G320, Marinette County
Other
8.0 MWWithdrawn / abandoned Marinette, WIMISO Mar 2003target 2005
Other project G321, Marathon County
Other
7.0 MWWithdrawn / abandoned Marathon, WIMISO Mar 2003target 2003
Onshore wind project J221, St. Croix County
Onshore wind
5.0 MWWithdrawn / abandoned St. Croix, WIMISO Aug 2011target 2014
Onshore wind project J765, Dodge County
Onshore wind
4.3 MWWithdrawn / abandoned Dodge, WIMISO Nov 2016target 2018
Battery storage project J1486, Waupaca County
Battery storage
2.5 MWWithdrawn / abandoned Waupaca, WIMISO Apr 2019target 2021
Onshore wind project G927, Calumet County
Onshore wind
2.0 MWWithdrawn / abandoned Calumet, WIMISO Dec 2007target 2014
Other project G582, Eau Claire County
Other
0.5 MWWithdrawn / abandoned Eau Claire, WIMISO Dec 2005target 2010
Page 5 of 5

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)