ONSHORE WIND Β· MISO

Onshore wind project G691, Vernon County

Onshore wind project G691, Vernon County is a 50.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Vernon County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2006 (completed)
  2. Withdrawn / abandonedNov 2009 (project stopped here)
  3. ConsentedNov 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G691
Grid region
MISO (Midcontinent)
Connection point (POI)
Westby - Cashton Tap 69 kV
Location
Vernon County, Wisconsin
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
16 October 2006
Agreement signed
17 November 2009
Proposed online date
July 2007
Withdrawn
November 2009

Location

Marker shows the centre of Vernon County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem