SOLAR Β· MISO

Solar project J1127, Green County

Solar project J1127, Green County is a 49.9 MW solar request withdrawn in the MISO interconnection queue, in Green County, Wisconsin, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedOct 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1127
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Albany - Bass Creek 138 kV Line Tap
Location
Green County, Wisconsin
Technology
Solar: 49.9 MW
Total requested
49.9 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
January 2021
Withdrawn
October 2019

Location

Marker shows the centre of Green County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Green County