πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project G281, Green County

Onshore wind project G281, Green County is a 130 MW onshore wind request withdrawn in the MISO interconnection queue, in Green County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2003 (completed)
  2. Withdrawn / abandonedNov 2004 (project stopped here)
  3. ConsentedNov 2004 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G281
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Green County, Wisconsin
Technology
Wind: 130 MW
Total requested
130 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
21 November 2003
Agreement signed
22 November 2004
Proposed online date
December 2005
Withdrawn
November 2004

Location

Marker shows the centre of Green County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Green County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem