United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project J825, Green County

Onshore wind project J825, Green County is a 99.9 MW onshore wind request withdrawn in the MISO interconnection queue, in Green County, Wisconsin, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J825
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
North Monroe - Albany 138kV Line
Location
Green County, Wisconsin
Technology
Wind: 99.9 MW
Total requested
99.9 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
September 2020
Withdrawn
January 2019

Location

Marker shows the centre of Green County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Green County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem