United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
SOLAR Β· MISOSolar project J1711, Green County
Solar project J1711, Green County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Green County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedNov 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1711
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- North Monroe 138kV Substation
- Location
- Green County, Wisconsin
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 24 June 2020
- Proposed online date
- September 2023
- Withdrawn
- November 2020
Location
Marker shows the centre of Green County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Green County
- Solar project J1706, Green CountySolar Β· 100 MW Β· agreement signed
- Gas project J3152, Green CountyGas Β· 160 MW Β· in study
- Surplus; J1305Other Β· 25.0 MW Β· in study
- Solar project J1305, Green CountySolar Β· 49.9 MW Β· built
- Solar project J1753, Green CountySolar Β· 300 MW Β· withdrawn
- Onshore wind project J738, Green CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project G281, Green CountyOnshore wind Β· 130 MW Β· withdrawn
- Onshore wind project J825, Green CountyOnshore wind Β· 99.9 MW Β· withdrawn
- Onshore wind project J584, Green CountyOnshore wind Β· 60.0 MW Β· withdrawn
- Onshore wind project G483, Green CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Solar project J1127, Green CountySolar Β· 49.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem