United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
ONSHORE WIND Β· MISOOnshore wind project J738, Green County
Onshore wind project J738, Green County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Green County, Wisconsin.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2016 (completed)
- Withdrawn / abandonedJul 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J738
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Green County, Wisconsin
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 11 November 2016
- Proposed online date
- September 2020
- Withdrawn
- July 2017
Location
Marker shows the centre of Green County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Green County
- Solar project J1706, Green CountySolar Β· 100 MW Β· agreement signed
- Gas project J3152, Green CountyGas Β· 160 MW Β· in study
- Surplus; J1305Other Β· 25.0 MW Β· in study
- Solar project J1305, Green CountySolar Β· 49.9 MW Β· built
- Solar project J1753, Green CountySolar Β· 300 MW Β· withdrawn
- Onshore wind project G281, Green CountyOnshore wind Β· 130 MW Β· withdrawn
- Solar project J1711, Green CountySolar Β· 100 MW Β· withdrawn
- Onshore wind project J825, Green CountyOnshore wind Β· 99.9 MW Β· withdrawn
- Onshore wind project J584, Green CountyOnshore wind Β· 60.0 MW Β· withdrawn
- Onshore wind project G483, Green CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Solar project J1127, Green CountySolar Β· 49.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem