Solar project J1305, Green County

Solar project J1305, Green County is a 49.9 MW solar request built and operating in the MISO interconnection queue, in Green County, Wisconsin, connecting to American Transmission Co..

Queue statusOperating
  1. PlanningQueued Apr 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMay 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J1305
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Albany - Bass Creek 138kV Line
Location
Green County, Wisconsin
Technology
Solar: 49.9 MW
Total requested
49.9 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
29 April 2019
Proposed online date
May 2023
Came online
May 2023

Location

Marker shows the centre of Green County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Green County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem