United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

GAS Β· MISO

Gas project J1843, Dane County

Gas project J1843, Dane County is a 12.0 MW gas request withdrawn in the MISO interconnection queue, in Dane County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2022 (completed)
  2. Withdrawn / abandonedJun 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1843
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Christiana 138 kV
Location
Dane County, Wisconsin
Technology
Gas: 12.0 MW
Total requested
12.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
6 January 2022
Proposed online date
March 2023
Withdrawn
June 2023

Location

Marker shows the centre of Dane County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Dane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem